Report for March 2019
- Report Date
- March 2019
Achievements this Period
- Work on final JIRAs completed
Issues
- None
Next Period
- Project closure
Milestones
Stage | Milestone | Due Date |
---|---|---|
Deliver | AppsLive deployment sign off | 04-Apr-2019 |
Close | Closure | 11-Apr-2019 |
- Approved budget
- 530.0 days
- Activity this month
- 2.9 days
- Activity this year
- 148.9 days
- Activity to date
- 527.5 days
- Estimate to complete current year
- 1.5 days
- Estimate to complete future years
- 0.0 days