Report for March 2019

Report Date
March 2019

Achievements this Period

  • Work on final JIRAs completed

Issues

  • None

Next Period

  • Project closure

 

Milestones

Stage Milestone Due Date
Deliver AppsLive deployment sign off 04-Apr-2019
Close Closure 11-Apr-2019
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
530.0 days
Activity this month
2.9 days
Activity this year
148.9 days
Activity to date
527.5 days
Estimate to complete current year
1.5 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation