Report for February 2018

Report Date
February 2018

IS Applications Infrastructure Programme Report for Programme Owner Stefan Kaempf

 

 

 

Section One: Programme Commentary, RAG and Resources Update

Overall Programme RAG: GREEN

Programme remain on target to deliver and close projects in this year, although we have agreed that a couple will now deliver in 2018-19.  

Section Two: Projects Not Started  

Project Info Programme Manager's Commentary
  All projects started

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

INF121

Migrate Core Databases to Oracle 12c

Milestones

07-Mar-2018 NewsDEV migrate to Oracle 12.2
22-Mar-2018 NewsTEST migrate to Oracle 12.2
30-Mar-2018 NewsTEST UAT complete
03-Apr-2018 NewsLIVE migrate to Oracle12.2

 

RAG Status / RAG change during last month

GREEN

 

Report by Chris Konczak for February 2018  

Achievements this Period

  • GEN migration to LIVE completed

Issues

  • None

Next Steps

  • NEWS remigration to Oracle 12.2
  • Decommission old NEWS and GEN databases
  • Lessons learned report on GEN to be written and used for APPS
  • Suspend project

 

INF127

LAMP / WIMP Platform Upgrade

Milestones

Date Milestone
23-Mar-2018 Acceptance Test of Platform
06-Apr-2018 Deploy New Platform
13-Apr-2018 Close

 

RAG Status / RAG change during last month

GREEN

Report by Maurice Franceschi (for Anne Mathison) for February 2018

Achievements :

  • Migrated Path to be tested in DEV - achieved
  • Complete setting up new platform in the environments (Dev, Test and Live) - achieved
  • Migrate Path to TEST -- achieved
  • Change business booking to request resourcing in February - achieved
  • Migrated Path to be tested in TEST - - achieved
  • Review and update draft of LAMP/WIMP findings on current platform - achieved
  • Look into RISK 7 re End Of Live YII to see if any progress can be made - not achieved

Issues

  • None

Next Steps :

  • fix TEST issues
  • Look into RISK 7 re End Of Live YII to see if any progress can be made  

INF128

Annual Infrastructure Rationalisation Decommissioning 17/18

Milestones

30-Mar-2018 Migrations completed/planned Deliver
13-Apr-2018 Project closure Close

 

RAG Status / RAG change during last month

Green

Report by David Watters for February 2018

Achievements

  • Registers for Windows 2008 machines updated - all outstanding entries chased & assigned
  • Registers for Windows 2012 & RedHat/CentOS6 servers updated
  • Individual servers decommissioned

Issues

  • None

Next steps

  • Windows 2008 servers to be switched off
  • Checks round 2017/18 listings to be finalised & wiki updated   

INF129

Database Resilience 17-18

Milestones              

Target Datesort descending   Title
 30-Mar-2018   Phase 1- WIKi App Tier to metro stretch cluster - Deploy to LIVE
 30-Apr-2018   Phase 1- - Closure
 31-May-2018   Phase 2 - Database move to VM & MSC - Analysis & Design Complete
 26-Oct-2018   Phase 2 - Stage 1 Database move to VM - Delivery Complete
 14-Dec-2018   Phase 2 - Stage 2- Wiki Database to MSC - Delivery complete
 21-Dec-2018   Project Close complete

                                                                             

RAG Status / RAG change during last month

 GREEN

 

 Report by Megan Graham for February 2018

 Achievements This Period

 

  • Wiki application DEV Milestone move VM to metro stretched cluster complete.

  • Wiki application TEST Milestone move VM to metro stretched cluster completed.

  • Issue with networks proved a 'blocker' for the application to move to LIVE.  Review on 28th February provided a decision to ensure Networks approval to LIVE or we halt the work and move it out to after the Wiki upgrade. 

  • Phase 2 - design of Wiki Database move to VM has commenced.

  • Closed Issues - 1) dependency on wiki COM039 - all planning has been completed and handover of DEV and TEST in progress.2) Network issue blocker in moving to LIVE - this has been closed as resource is not assigned and plan of action in progress.

 Issues

None

 Next Steps

  • Move Application Tier to LIVE. 

  • Handover DEV and TEST to Wiki upgrade Project COM039.

  • Design on Phase 2 - Stage 1 - issued in draft

 

   

 

INF130

Annual DR Test and Review 17-18

Milestones

Target Datesort descending Title Stage
09-Mar-2018 Planning Review Plan

RAG Status / RAG change during last month

GREEN

 Report by David Gibbons for February 2018

Achievements this Period

  • Discussions with Project sponsor
  • Project Brief development  started
  • Discussions with ITI re ENT024

Ongoing actions

  • Planning
  • Publish brief

Planned actions

  • Joint Kick off meeting
  • Sign off on Brief and planning
  • Regular project reviews

 

 

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

INF123

16-17 Provisioning of Python environment

Closed

INF126

Bamboo Recovery

Closed

INF132

Application Monitoring Procurement

Withdrawn - no sponsor funding

 

 