Report for October 2017

Report Date
October 2017

Achievements this Period

  • Decision made to alter the "SQLNET.ORA” to “ALLOWED_LOGON_VERSION_SERVER = 8” which will allow us to proceed with migrating GEN Dev to GEN TEST. This decision will also apply to the APPS migrations, which contain a number for ColdFusion 10 applications.
  • Project milestones have been replanned, and resource secured. This has been approved.
  • Three technical issues with GEN which had been raised in JIRA have been resolved.

 

Issues

  • There will be a budget review in November to determine the number of extra days required to complete the project.

 

Next Steps

  • GEN to be migrated into TEST
  • Integration testing to commence
  • LIVE environment to be upgraded to 12.2 ahead of the planned migrations. The only application on LIVE is Bamboo.
  • Review required of the Bamboo plans to determine if any of them require to be approved and enabled for the GEN applications.

Milestones

10-Nov-2017 GENDEV Post-migration Checks
15-Dec-2017 GenTEST post migration (integration) sign off
17-Jan-2018 GenTEST Acceptance sign off
19-Jan-2018 Re-estimation for AppsLive
30-Jan-2018 GenLive deploy to LIVE
14-Feb-2018 GenLive deployment sign off
02-Mar-2018 AppsDEV build sign off
23-Mar-2018 Test environment build for AppsTEST complete
04-Apr-2018 AppsTEST integration sign off
20-Apr-2018 AppsTEST Acceptance sign off
07-May-2018 Live environment build for AppsLive complete
15-May-2018 AppsLive deploy to LIVE
31-May-2018 AppsLive deployment sign off
15-Jun-2018 Closure
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
81.0 days
Activity this month
12.0 days
Activity this year
65.0 days
Activity to date
271.0 days
Estimate to complete current year
115.0 days
Estimate to complete future years
0.0 days