Report for September 2017
- Report Date
- September 2017
Achievements in Last Period
- On-going dialogue with Student Systems to update data document awaiting approval, further queeies raised by them
Issues
- WP8 Meeting held with DevelopmentTechnology and RIS resource to understand fuller requirements of this activity, however concerns raise that there may be more depth work required. Meeting with St Andrews University colleagues who are looking at this at present, has still to be arranged by RIS this is to help gauge if this actually is a larger project and more funding to complete.
- WP4 still to be progressed likelihood this will be a business process and no technical resource required
- Review impact of delay and unplanned budget required for next financial year 17/18 review with Programme Owner and Business Lead, revise project milestones
- Limited availability from PM to progress
Next Steps
- Discussion to be held with RIS on status of project
- WP1 - Student System approval provided and set up EPPN
- WP8 - Meeting to be scheduled with St Andrews University
- WP4 - Arrange meeting with RSO and RGS together with HR resource
- Close project
The project Status is RED as limited progress has been made, milestones to be confirmed and budget to be approved for 17/18 financial year.
| TBC | WP1 Delivery |
| TBC | WP4 Delivery |
| TBC | WP8 Delivery |
| TBC | Project Closure |
- Approved budget
- 25.0 days
- Activity this month
- 0.3 days
- Activity this year
- 15.4 days
- Activity to date
- 15.4 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days