Report for July 2017
- Report Date
- July 2017
Morna Findlay (IS Apps Programme Manager) for Zoe Lewandowski (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Commentary
The programme manager considers that overall the programme is GREEN, as all projects which were not withdrawn were delivered this year and within the programme budget.
As the remaining project in the programme (HRS092) was already fully resourced, the HR Balance row has been reduced from 9 days to 0 days: 9 days were transferred to the USG portfolio budget.
This has resulted in a reduction to the programme budget from 230 days to 221 days.
Risk - Erecruitment Licencing - NCA required
The e-recruitment contract needs to be updated by October 2017. The original 5 year contract concludes in October and any extension for a further year must be arranged by October. An extension would be done as a Non-Competitive Action (NCA) and this is essential to be licensed to continue using eRecruitment.
Projects in Progress: summary
HRS091 - Closed this month.
HRS092 - GREEN
Forward Look for August 2017
Resources to 31/07/2017
HRS092 is the only remaining project this year. It is planned to close in 17/18.
Section Two: Projects Not Started
There are no approved projects planned to this month. The following projects will start later in the year.
AP17-18: APEX Tomcat 7 End of Life |
AP17-18: HESA Staff Return 17/18 |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||
Working Time Capture and Reporting ( was Enhancing Employment Technical Implementation) Category: Core Funded Compliance Milestones None
RAG Status BLUE |
Report by Susan Duff for July 2017Achievements in Last Period
Issues
Next Period
|
||||||||
HRS092 (AP67-034) HESA Staff Return 16/17 Category : Core-funded Compliance Milestones
RAG Status GREEN |
Report by Anne Mathison for July 2017AchievementsDEV and TEST have been refreshed during JULY in preparation for HESA LIVE Testing and checking out any issues that arise in August. RESAST has had the 31st July file provided loaded on 1-Aug in preparation for HESA Live Testing Issues
Next Steps
Project has a RAG status of GREEN
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
AP67-035 Upgrade eRecruitment Database to Oracle 12c CategoryL Compliance |
This project has been withdrawn from the current year as the end. of life for Oracle 11g has been extended till 2020 . There may be no requirement for the upgrade if erecruitment is replaced. This project will therefore be planned for 18/19-19/20. |
Category:Compliance |
Report by Anne Mathison Project Closure Milestone achieved on 25-Nov-16, Project Completion Report available on the website |
HRS086 eRecruitment Proof of Concept Category: Discretionary, Funded |
Report by Susan McKeown Project Closure Milestone achieved on 25-Aug-15 Project's Completion Report is available on the website. |
HRS085 HESA Staff Return 14/15 Category: Compliance |
Report by Anne Mathison Project Closure Milestone achieved on 20-Nov-15 Project's Completion Report is available on the website. |
Category: Funded |
Report by Susan McKeown Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website. |
HRS088 HR Transformation: Governance and Planning Category: Compliance |
Report by Susan McKeown Project Closure Milestone achieved on 18-Dec-15 Project's Completion Report is available on the website |
HRS084 Enhancing Employment Analysis Category: Discretionary |
Report by Franck Bergeret Project Closure Milestone achieved on 18-Feb-16 Project's Completion Report is available on the website |
HRS090 HESA Staff Return 15/16 Category : Compliance |
Report by Anne Mathison Project Closure Milestone achieved on 24-Nov-16 Project's Completion Report is available on the website |
HRS091 Erecruitment Upgrade |
Report by Muriel Mewisson Project Closure Milestone achieved on 2-Jun-2017 Project's Completion Report is available on the website |
Working Time Capture and Reporting |
Report by Susan Duff Project Closure Milestone achieved on 13-Jul-2017. Project's Completion Report is available on the website. |