July 2016

Report Date
July 2016

Achievements this Period

  • Brief completed with estimate

 

Issues

  • Planning milestone needs to be moved as sponsor is on annual leave and budget cannot be approved. Project is RED again as a result of this.

 

Next Steps

  • Brief signed off and budget approved
  • Book Dev Tech to start in September

 

Milestones

26-Aug-2016Planning sign off
16-Sep-2016Systems Analysis and design complete
14-Oct-2016Build - APPSLive
21-Oct-2016Build - NEWSLive
04-Nov-2016Build GENLive
08-Nov-2016Build Sign off
16-Nov-2016Integration - Test Environments Built
23-Nov-2016Integration - APPSLive migrated
01-Dec-2016Integration - GENLive migrated
06-Dec-2016Integration - NEWSLive migrated
21-Dec-2016Integration sign off review
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days