January 2016
- Report Date
- January 2016
Meeting with vendors went ahead as planned in December and provided a good overview of the current market and what is on offer.
I have sufficient information now to produce my paper recommending next steps.
It is expected to have this paper completed by early February 2016.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days