Report for July 2015

Report Date
July 2015

Achievements in Last Period

  • Initial analysis draft circulated to stakeholders
  • First round of feedback received and incorporated in analysis
  • Second draft circulated to stakeholders
  • Milestones moved out to allow more time for consultaion

Issues

  • No issues to reportdaft

Next Steps

  • Incorporate second round of feedback
  • Review and sign off analysis
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
20.0 days
Activity this month
8.0 days
Activity this year
12.0 days
Activity to date
12.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
8.0 days