July 2015

Report Date
July 2015

Achievements in Last Period

  • Draft business case outline and complete business case - complete:
    • Complete baseline financial and usage data (Jim) - as complete as possible, baseline utilisation for 6 of the 10 of the scientific instruments in question determined, and cost and revenue at overall NMR and Mass Spec grouping level determined.
    • Complete identification of high-level requirements by role - complete
    • High-level review of existing systems to determine overlap - complete
  • High-level estimate of work needed if existing systems are not sufficient - complete
  • Project Closure agreed

Issues

  • None

Next Steps

  • None
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
5.0 days
Activity this month
3.0 days
Activity this year
5.0 days
Activity to date
5.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days