Monthly Progress Report

Report Date
April 2014

Achievements this period

  • Meterology successfully deployed  on  the new migrated live infrastructure
    • Disaster Recovery tasks successfully completed
    • Migrated existing database onto new environment
    • Ensured all meters directed to the METERology system on the new environment
    • Handover to IS Apps Production Team successfully completed including all operational documentation

Issues

  •  No issues to report

Next steps

  • Complete Deployment Sign off review and Closure

 

 Projected Milestones 

 

Dates 
9-May-2014DSOR and Closure

 

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
62.0 days
Activity this month
6.0 days
Activity this year
59.0 days
Activity to date
59.0 days
Estimate to complete current year
3.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.