Monthly Progress Report
- Report Date
- April 2014
Achievements this period
- Meterology successfully deployed on the new migrated live infrastructure
- Disaster Recovery tasks successfully completed
- Migrated existing database onto new environment
- Ensured all meters directed to the METERology system on the new environment
- Handover to IS Apps Production Team successfully completed including all operational documentation
Issues
- No issues to report
Next steps
- Complete Deployment Sign off review and Closure
Projected Milestones
| Dates | |
| 9-May-2014 | DSOR and Closure |
- Approved budget
- 62.0 days
- Activity this month
- 6.0 days
- Activity this year
- 59.0 days
- Activity to date
- 59.0 days
- Estimate to complete current year
- 3.0 days
- Estimate to complete future years
- 0.0 days