Organisation
Work/Task Breakdown
- Clone Oracle Live to Dev and Test
- Clone Dev will not be required assuming HRS081 continues to completion at the start of December
- Clone TEST
There will then be three phases
- Phase 1 Pre-requisite TYE Oracle Patches (e.g. Roll Up Patches 7 / Family Pack )
- Phase 2 Tax Year End and Security Patches and P60s Updates
- Phase 3 Post Budget. This phase may not be required if no post budget changes are needed.
Each Phase will incorporate
- Investigation into work required for this Phase and create a list of the required patches
- Check the project requirements for the HR-Dev environment, apply patches successfully to HR-Dev, carry out all post patching checks.
- Apply patches successfully to HR-Test, carry out all post patching checks.
- Support Acceptance testing
- Deploy to LIVE
Phase 2 will include the changes required to the P60 form for 14/15.
Resource Estimates and Costs
Internal
Resources and Skills;
- HR, Payroll and Pensions will be required to test and sign off patching in each of the three environments.
- IS Applications Support, IS SASG Dev and Payroll and Pensions Technical Support will review available patches and jointly agree what are to be applied.
- IS Applications Technical Architect will be required to complete clone work and identify and apply security patches.
- IS USG Dev will amend the P60 form as agreed with the Payroll and Pensions Technical Support
Cost;
- No additional costs are expected for this project (IS Applications days are covered by Core Funding)
External
- None identified