Organisation

 

Work/Task Breakdown

Agreement has been reached with all IS APPS resource managers that the high level plan and workload is acceptable for their teams.

Initiate / Plan

Brief  - Project Services - All

Grouper Version Review - Development Team

Determine Scope of known Error Inclusion - all

High Level Design - Development Team

Review Design

Create Plan - Project Services

Detailed Design - IS APPS, Service Management

Execute

Phase 1 - Push

Management - Project Services

SOA Environments - Dev Tech

Design - Development Team

Develop - Development Team

Peer Test - Development Team

Deploy - Dev Tech

TEST - Service Management / User Groups

Deploy to LIVE - Tech Man/AppMan

Phase 2  - Inbound

Management - Project Services

SOA Environments - Dev Tech

Design - Development Team

Develop - Development Team

Peer Test - Development Team

Deploy - Dev Tech

TEST - Service Management / User Groups

Deploy to LIVE - Tech Man/AppMan

Phase 3 - Pull

Management - Project Services

SOA Environments - Dev Tech

Design - Development Team

Develop - Development Team

Peer Test - Development Team

Deploy - Dev Tech

TEST - Service Management / User Groups

Deploy to LIVE - Tech Man/AppMan

Phase 4 - Grouper

Management - Project Services

Environments - Dev Tech/ITI

Design - Development Team

Develop - Development Team

Peer Test - Development Team

Deploy - ITI

TEST - Service Management / User Groups

Deploy to LIVE - ITI

     

Close/Review

Closure - All

Resources Skills and Cost

 

The breakdown of resources for the project will be as follows :-

 

IS Apps Project Services - 61 days IS Apps Dev Team - 183 days IS Apps Dev Tech - 46 days IS Apps Prod App Man - 19 days IS Apps Prod Tech Man - 9.5 days IS ITI - 8.5 days IS Apps Serv Mgt:  - 130 Days  