December 2014

Report Date
December 2014

Achievements in Last Period

  • Build continued as planned

Issues

  • no issues of note
  • no risks of note

Next Steps

  • review plan with team as we may be ahead of schedule

 

Milestones

 

04-Mar-2015Build
18-Mar-2015Acceptance sign-off
25-Mar-2015Delivery
17-Apr-2015DSOR
29-Apr-2015Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
130.0 days
Activity this month
37.0 days
Activity this year
74.0 days
Activity to date
74.0 days
Estimate to complete current year
56.0 days
Estimate to complete future years
0.0 days