Report for November 2019

Report Date
November 2019

Status

A new potential security and/or personal data issue has been identified regarding the data captured by the devices using the current design, and a review of this is underway.   No other activities will be progressed until this has been closed off satisfactorily.    As a result, the original estimated completion timescale for the project is unlikely to be met.   The project is not flagged as Amber at this stage as there is no wider impact at this stage, but this will change if we do not have a satisfactory way forward identified  by the end of January.

 

Issue:

No resources have been identified for actual deployment of devices to sites.

 

Risk:

There is a risk that the investigation in to the potential issue noted under 'status' above, could result in a delay to project timescales, which in the worst case could result in a failure to deliver the key objectives of the project.

 

Next Steps:

  • Investigate potential issue noted under 'status' above, then agree way forward.
  • Assuming the potential issue is resolved satisfactorily, the we can progress with:
    • Planning to complete remaining deliverables (no date set for this yet, and sometime in October is estimated earliest date due to other priorities within the IoT team).
      • PIA
      • Completion of Lilee device builds.
      • Agree how devices will be deployed to site.
      • Establish the operational service including DR procedure.
      • Agreed plan for further service roll-out.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Lilee
Code
WCD003
Programme
WCDI IoT Programme
Management Office
ISG PMO
Project Manager
Stephen Taylor
Project Sponsor
Simon Chapple
Current Stage
Execute
Status
In Progress
Project Classification
Transform
Start Date
20-May-2019
Planning Date
20-Jun-2019
Delivery Date
20-Dec-2019
Close Date
31-Jan-2020
Overall Priority
Normal
Category
Discretionary

Documentation