Report for October 2019

Report Date
October 2019
Status

No activity since August's report, so this remains as per last August:

  • Planning, project brief, and initial risk assessment completed.   This risk assessment has confirmed that a PIA will be required as personal data, in the form of UUNs, will be captured.
  • Components for the devices were purchased and the production method documented.
  • Lilee s/w security issues from previous build fixed. 
  • Method established fro deploying software upgrades to Lilee devices at scale.
  • Students were employed through June and July and they build the bulk of the Lilee devices, although more work is required to complete this.
  • The Server has been stood up and Python updated to v3.

 

Issue:

No resources have been identified for actual deployment of devices to sites.

 
Next Steps:
  • Planning to complete remaining deliverables (no date set for this yet, and sometime in October is estimated earliest date due to other priorities within the IoT team).
    • PIA
    • Completion of Lilee device builds.
    • Agree how devices will be deployed to site.
    • Establish the operational service including DR procedure.
    • Agreed plan for further service roll-out.

 

Notes:
  • As planning for remaining activities has not completed, the current project delivery completion date of 20th Dec, and project closure date of 31st Jan are estimates.

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Lilee
Code
WCD003
Programme
WCDI IoT Programme
Management Office
ISG PMO
Project Manager
Stephen Taylor
Project Sponsor
Simon Chapple
Current Stage
Execute
Status
In Progress
Project Classification
Transform
Start Date
20-May-2019
Planning Date
20-Jun-2019
Delivery Date
20-Dec-2019
Close Date
31-Jan-2020
Overall Priority
Normal
Category
Discretionary

Documentation