Report for August 2019
- Report Date
- August 2019
Status
- Planning, project brief, and initial risk assessment completed. This risk assessment has confirmed that a PIA will be required as personal data, in the form of UUNs, will be captured.
- Components for the devices were purchased and the production method documented.
- Lilee s/w security issues from previous build fixed.
- Method established fro deploying software upgrades to Lilee devices at scale.
- Students were employed through June and July and they build the bulk of the Lilee devices, although more work is required to complete this.
- The Server has been stood up and Python updated to v3.
Issue:
No resources have been identified for actual deployment of devices to sites.
Next Steps:
- Planning to complete remaining deliverables (no date set for this yet, and sometime in October is estimated earliest date due to other priorities within the IoT team).
- PIA
- Completion of Lilee device builds.
- Agree how devices will be deployed to site.
- Establish the operational service including DR procedure.
- Agreed plan for further service roll-out.
Notes:
- As planning for remaining activities has not completed, the current project delivery completion date of 20th Dec, and project closure date of 31st Jan are estimates.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days