Report for September 2012

Report Date
September 2012

Achievements in Last Period

  • Planning completed and signed off.

Issues

  • No issues to report at this stage

Next Steps

  • UWS will complete business analysis, which will be reviewed by Development Team.

Milestones

Target dateTitle
14-Sep-2012Planning Review
29-Oct-2012Analysis Review
15-Nov-2012Design Review
07-Dec-2012Build Review
14-Dec-2012Integration Review
21-Jan-2013Acceptance Review
24-Jan-2013Delivery
08-Feb-2013Deployment Review
21-Feb-2013Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
53.0 days
Activity this month
1.8 days
Activity this year
3.3 days
Activity to date
3.8 days
Estimate to complete current year
50.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Ajax Enhancements
Code
UWS002
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Initiate
Status
Withdrawn
Start Date
23-Jul-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
07-Dec-2012