Report for September 2012
- Report Date
- September 2012
Achievements in Last Period
- Planning completed and signed off.
Issues
- No issues to report at this stage
Next Steps
- UWS will complete business analysis, which will be reviewed by Development Team.
Milestones
Target date | Title |
---|---|
14-Sep-2012 | Planning Review |
29-Oct-2012 | Analysis Review |
15-Nov-2012 | Design Review |
07-Dec-2012 | Build Review |
14-Dec-2012 | Integration Review |
21-Jan-2013 | Acceptance Review |
24-Jan-2013 | Delivery |
08-Feb-2013 | Deployment Review |
21-Feb-2013 | Closure |
- Approved budget
- 53.0 days
- Activity this month
- 1.8 days
- Activity this year
- 3.3 days
- Activity to date
- 3.8 days
- Estimate to complete current year
- 50.0 days
- Estimate to complete future years
- 0.0 days