Report for August 2012

Report Date
August 2012

Achievements in Last Period

Planning is in progress

Issues

Planning has been slightly hampered due to resource availability in UWS, simultaneous project planning for UWS and on-going resourcing discussions.

Next Steps

  • Complete planning
  • Start Business Analysis

Milestones

Target dateTitle
14-Sep-2012Planning Review

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
53.0 days
Activity this month
1.6 days
Activity this year
2.3 days
Activity to date
2.3 days
Estimate to complete current year
50.4 days
Estimate to complete future years
0.0 days

Project Info

Project
Ajax Enhancements
Code
UWS002
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Initiate
Status
Withdrawn
Start Date
23-Jul-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
07-Dec-2012