June 2019

Report Date
June 2019

The outputs of this projects will now be incorporated within the activities and projects to build the new web services and replacement EdWeb platform.

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
University Webservices
Code
UWP098
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
Stuart McVicar
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
13-Feb-2019
Planning Date
22-Feb-2019
Delivery Date
30-Jun-2019
Close Date
05-Jul-2019
Overall Priority
Normal
Category
Discretionary

Documentation

Not available.