Report for March 2018

Report Date
March 2018

Achievements in Last Period

  • No work carried out on the project in the last period.

Issues

  • Issue raised that project cannot be closed till final decision received from senior management. 

Next Steps  

  • Final decision from senior management regarding the future of the project.
  • Closure report
  • Decision on future of the current Talks system.
Project Status
RAG Status
Time
RED
Cost
RED
Scope
RED
Overall
RED
RAG Commentary
Issue - In agreement with the project sponsor, the project has been halted as the technical assessment of Oxford @Talks platform deemed that the software as not fit for purpose for the UoE. The required changes could not be delivered within the agreed budget/timescales. No activity was carried out last month. The project sponsor is awaiting final decision from LTW senior management before project is withdrawn.
Change Status
Activity
Approved budget
128.0 days
Activity this month
1.5 days
Activity this year
29.8 days
Activity to date
37.9 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Deliver Talks@Ed as a University-wide Service
Code
UWP019
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
Sonali Nakhate
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
17-Nov-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
20-Apr-2018
Programme Priority
3
Overall Priority
Normal
Category
Discretionary