Report for January 2018

Report Date
January 2018

Achievements in Last Period

  • Project Brief completed.
  • High level plan and estimates produced.
  • Planning Review milestone submitted to WIS for approval.

Issues

  • Availability of DevTech and Software development resources will impact the timescales.

Next Steps 

  • Sign off Planning Review milestone.
  • Start Business Analysis activity, requirements gathering exercise and technical evaluation will make the scope of the project clearer.
  • Start technical evaluation of open source software.

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
128.0 days
Activity this month
17.0 days
Activity this year
17.0 days
Activity to date
25.0 days
Estimate to complete current year
103.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Deliver Talks@Ed as a University-wide Service
Code
UWP019
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
Sonali Nakhate
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
17-Nov-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
20-Apr-2018
Programme Priority
3
Overall Priority
Normal
Category
Discretionary