- Report Date
- January 2018
Achievements in Last Period
- Project Brief completed.
- High level plan and estimates produced.
- Planning Review milestone submitted to WIS for approval.
Issues
- Availability of DevTech and Software development resources will impact the timescales.
Next Steps
- Sign off Planning Review milestone.
- Start Business Analysis activity, requirements gathering exercise and technical evaluation will make the scope of the project clearer.
- Start technical evaluation of open source software.
- Approved budget
- 128.0 days
- Activity this month
- 17.0 days
- Activity this year
- 17.0 days
- Activity to date
- 25.0 days
- Estimate to complete current year
- 103.0 days
- Estimate to complete future years
- 0.0 days