Report for November 2017
- Report Date
- November 2017
Achievements in Last Period
- Project Started
Issues
- None
Next Steps
- Project Brief
- planning
- estimations
- Business Analysis
- Approved budget
- 90.0 days
- Activity this month
- 0.3 days
- Activity this year
- 0.5 days
- Activity to date
- 0.5 days
- Estimate to complete current year
- 87.4 days
- Estimate to complete future years
- 0.0 days