Report for August 2017
- Report Date
- August 2017
Achievements in Last Period
- Progression of Contract Agreement (SaaS agreement)
Issues
Delay in gaining sign off for the SaaS Agreement. This is now expected 01/09/17 (see issue 11)
Next Steps
- Contract Award
The contract at this time is due to commence on 01/08/17
| Target Date |
Title |
|---|---|
| 03-Aug-2017 | Award Contract |
| 01-Sep-2017 | SaaS Sign Off |
| 08-Sep-2017 | Closure |
- Approved budget
- 5.0 days
- Activity this month
- 4.1 days
- Activity this year
- 4.1 days
- Activity to date
- 112.0 days
- Estimate to complete current year
- 1.2 days
- Estimate to complete future years
- 0.0 days
