Report for July 2016
- Report Date
- July 2016
Achievements in Last Period
- Project Kick-off meeting complete.
- Project objectives agreed.
- Project approach agreed.
- Project team members identified.
- Project Brief signed off.
- Regular weekly checkpoint meetings scheduled with Project Sponsor.
- First two workshops with stakeholders scheduled.
Issues
- No issued identified this reporting period.
Next Steps
- Workshops with stakeholders.
- Development of mapping of what is required and prioritised further work / actions.
Target Date / Title
| 09-Aug-2016 | Deliver Workshop 1 |
| 24-Aug-2016 | Deliver Workshop 2 |
| 31-Aug-2016 | Deliver reviewed and signed-off mapping and prioritised further work / actions |
- Approved budget
- 20.0 days
- Activity this month
- 3.0 days
- Activity this year
- 3.0 days
- Activity to date
- 3.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 10.0 days