September 2014

Report Date
September 2014

Achievements in the last period

  • Project signed off as complete
  • Handover to UWP010 complete
  • Project approved for closure by WIS
  • Project Closed

Issues

  • None

Next

  • NA
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
66.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
66.4 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Migration Preparation of Current Content and Data Structures
Code
UWP009
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Colin Forrest
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
22-Nov-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Sep-2014
Overall Priority
Normal