August 2014

Report Date
August 2014

Achievements in the last period

  • Migration code has successful passed through the UWP code checks.
  • Code has now been added to the UWP SVN for version control as the Drupal release develops.
  • All must have JIRAs for the beta release have been resolved.
  • The migration handbook has been worked through by the UWP team and verbally accepted.  It is also under the version control process.
  • Due to staff restructuring between the Software Dev teams we have successfully handed over the unique project work to our new developer.  They will now take the migration developments forward in project UWP010. 

Issues

  • The restructuring in Software Dev had not initially taken account of the handover needs for the UWP migration work.  This was however successfully worked through to a satisfactory conclusion.   

Next steps

  • Formally close the project.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
66.0 days
Activity this month
4.0 days
Activity this year
0.0 days
Activity to date
65.6 days
Estimate to complete current year
0.4 days
Estimate to complete future years
0.0 days

Project Info

Project
Migration Preparation of Current Content and Data Structures
Code
UWP009
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Colin Forrest
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
22-Nov-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Sep-2014
Overall Priority
Normal