August 2014
- Report Date
- August 2014
Achievements in the last period
- Migration code has successful passed through the UWP code checks.
- Code has now been added to the UWP SVN for version control as the Drupal release develops.
- All must have JIRAs for the beta release have been resolved.
- The migration handbook has been worked through by the UWP team and verbally accepted. It is also under the version control process.
- Due to staff restructuring between the Software Dev teams we have successfully handed over the unique project work to our new developer. They will now take the migration developments forward in project UWP010.
Issues
- The restructuring in Software Dev had not initially taken account of the handover needs for the UWP migration work. This was however successfully worked through to a satisfactory conclusion.
Next steps
- Formally close the project.
- Approved budget
- 66.0 days
- Activity this month
- 4.0 days
- Activity this year
- 0.0 days
- Activity to date
- 65.6 days
- Estimate to complete current year
- 0.4 days
- Estimate to complete future years
- 0.0 days