Report for March 2014

Report Date
March 2014

Achievements

  • Polopoly TEST DB upgraded to 11g
  • UAT completed successfully
  • Polopoly LIVE DB upgraded to 11g
  • Remaining work and milestones re-planned

Issues

  • Revised budget: The project will require an additional 18 days to complete. The days are available from programme budget, the revised estimate agreed and changes submitted to WIS.

Next steps

  • Build of new TEST Front End servers
  • Integration testing of TEST Front End servers
  • DR and load testing of TEST Front End servers
Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
132.0 days
Activity this month
31.0 days
Activity this year
121.0 days
Activity to date
121.0 days
Estimate to complete current year
19.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Polopoly Database Upgrade to 11g and Web Server Replacement
Code
UWP007
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
06-Sep-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Jun-2014
Category
Compliance