Report for March 2014
- Report Date
- March 2014
Achievements
- Polopoly TEST DB upgraded to 11g
- UAT completed successfully
- Polopoly LIVE DB upgraded to 11g
- Remaining work and milestones re-planned
Issues
- Revised budget: The project will require an additional 18 days to complete. The days are available from programme budget, the revised estimate agreed and changes submitted to WIS.
Next steps
- Build of new TEST Front End servers
- Integration testing of TEST Front End servers
- DR and load testing of TEST Front End servers
- Approved budget
- 132.0 days
- Activity this month
- 31.0 days
- Activity this year
- 121.0 days
- Activity to date
- 121.0 days
- Estimate to complete current year
- 19.0 days
- Estimate to complete future years
- 0.0 days