Report for December 2019
- Report Date
- December 2019
Achievements this period
- Evaluation of bids - mandatory requirements evaluation conducted
Issues
- Unfortunately none of the suppliers successfully passed the mandatory question exercise
- Consensus meetings therefore cancelled
- With no suppliers left the team asked Procurement for advice. There is the possibility of the NCA (non-compliance action) route where we cancel the procurement but this has strict rules and need to justify.
- In the meantime project is on hold and that further action is subject to senior management's decision (escalated to Gavin McLachlan)
See notes of meeting 5 December and piccl 10
Next Steps
- Has been escalated to Gavin McLachlan and the team await his advice before moving forward
Milestones
|
20-Dec-2019 |
|
|
24-Jan-2020 |
|
|
31-Jan-2020 |
|
|
14-Feb-2020 |
|
|
13-Mar-2020 |
|
|
10-Apr-2020 |
|
|
24-Apr-2020 |
These milestones are now out of date - once we know how to proceed with the procurement we can reschedule the dates
- Approved budget
- 120.0 days
- Activity this month
- 3.0 days
- Activity this year
- 34.0 days
- Activity to date
- 65.0 days
- Estimate to complete current year
- 55.0 days
- Estimate to complete future years
- 0.0 days