Report for September 2019
- Report Date
- September 2019
Achievements this period
-
Scenarios for supplier evaluation demonstrations agreed by team, via a user story workshop
-
Contextual metrics document reviewed with draft text added
-
Updated procurement strategy in line with project team feedback
-
Clarifications provided on mandatory requirements
Issues
- Requirements Specification milestone has passed, but expected to be completed in first week of October in time for ITT approval
- Procurement strategy still to be signed off by Director of Procurement; this will be resolved early in October, in advance of the Invitation to Tender (ITT)
- Discussion in progress to agree how to incorporate the requirement for 'encryption at rest' - clarification being sought from Information Security Team
Next Steps
- Sign off procurement strategy
- Finalise the mandatory requirements and contextual metrics to be put forward to bidders to demonstrate; alongside the evaluation process and weightings.
- Complete requirements specification and ITT documentation for tender; ready for approval by the Core Systems Programme Board
- Approved budget
- 120.0 days
- Activity this month
- 4.8 days
- Activity this year
- 14.6 days
- Activity to date
- 45.5 days
- Estimate to complete current year
- 74.6 days
- Estimate to complete future years
- 0.0 days