Report for August 2019

Report Date
August 2019

Achievements this period

  • Good progress was made on defining the mandatory requirements for the procurement, with an initial draft produced

  • The IS owned procurement question sets have been validated by the project team

  • Updated procurement strategy for review by project team

Issues

  • Procurement strategy still to be signed off by project sponsor; this will be resolved in the first half of September, in advance of the Invitation to Tender (ITT)
  • The project milestones were reviewed, and revised milestones approved following discussions with the project team and the project sponsor (programme owner).  Additional time is required to complete the mandatory requirements, the contextual metrics document and the scenarios we want to see bidders demonstrate.  In order to complete these tasks, and taking into account upcoming holidays for key members of the team during September, it is expected the requirements specification will now be completed by the end of September.  Subsequent milestones were pushed back as a consequence.

Next Steps

  • Sign off procurement strategy
  • Finalise the mandatory requirements, contextual metrics and the scenarios to be put forward to bidders to demonstrate; alongside the evaluation process and weightings.
  • Complete requirements specification for tender; ready for approval by the Core Systems Programme Board
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
120.0 days
Activity this month
9.8 days
Activity this year
9.8 days
Activity to date
40.7 days
Estimate to complete current year
79.3 days
Estimate to complete future years
0.0 days

Project Info

Project
Development and Alumni CRM Procurement
Code
USG014
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Kate Brook
Current Stage
Execute
Status
In Progress
Project Classification
Grow
Start Date
19-Apr-2019
Planning Date
30-Apr-2019
Delivery Date
13-Mar-2020
Close Date
27-Mar-2020
Overall Priority
Normal
Category
Discretionary

Documentation