Current project status Report Date RAG Budget Effort Completed Effort to complete December 2019 RED 120.0 days 65.0 days 55.0 Content Status In Progress Current Stage Execute Start Date Friday, 19 April 2019 Planning Date Tuesday, 30 April 2019 Delivery Date Friday, 13 March 2020 Close Date Friday, 27 March 2020 Project information Project Code USG014 Programme USG Portfolio Projects (OTHUSG) Session 19/20 18/19 Organisational Unit University Secretarys Group Project Management Office (if relevant) ISG PMO Responsibility Applications Development and Operations Project Category Discretionary Project Classification Grow Funding Source Sponsor Overall Priority Normal