- Report Date
- October 2019
Achievements this period
- The project was formally closed on the 25 october 2019. The Closure Report is now available.
Next Steps
- None - project is closed.
- Approved budget
- 50.0 days
- Activity this month
- 0.8 days
- Activity this year
- 10.1 days
- Activity to date
- 42.6 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days
This article was published on