- Report Date
- September 2019
Achievements this period
- Closing Report was drafted and discussed with Programme Manager and ITI
- Clarification of Closing Report finalised with ITI
Issues
- Change of Closing Milestone to 11th October 2019 (was 13/09/2019) was submitted and approved by WIS on Friday, 20/09/2019
Next Steps
- Closing Report to be finalised and signed off by SRA and Communications
- Closing Project
- Approved budget
- 50.0 days
- Activity this month
- 4.7 days
- Activity this year
- 9.2 days
- Activity to date
- 41.8 days
- Estimate to complete current year
- 1.5 days
- Estimate to complete future years
- 0.0 days