June Report 2019

Report Date
June 2019

Achievements this period

  • First combined meeting for Embargo & Clearing with all Stakeholders took place in order to discuss further steps
  • Development of the SharePoint Site was inititiated
  • All Meetings within the Clearing Period are set up
  • Project Brief was signed off

Issues

  • SharePoint Development might primarily be conductible in June due to the limited availability of the resources from July onwards

Next Steps

  • Further clarification and finalisation of the required SharePoint Development required
  • Project Services Intern to start SharePoint training to potentially be able to cover
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
SharePoint Development potentially at risk due to restricted time availability of booked resource and outstanding requirements still to be confirmed.
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
Planning milestone completed 7 June , one month later than expected (was 6 May)
Activity
Approved budget
50.0 days
Activity this month
3.8 days
Activity this year
13.8 days
Activity to date
13.8 days
Estimate to complete current year
14.0 days
Estimate to complete future years
26.0 days

Project Info

Project
Clearing 2019
Code
USG013
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
Victoria Weinsberg
Project Sponsor
Rebecca Gaukroger
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
11-Mar-2019
Planning Date
06-May-2019
Delivery Date
06-Aug-2019
Close Date
25-Oct-2019
Overall Priority
Normal
Category
Compliance

Documentation