May Report 2019

Report Date
May 2019

Achievements this period

  • Kick Off Meeting with SRA & Colleges took place in order to discuss potential changes and additional requirements
  • Project Brief drafted

Issues

  • Project Brief submission to WIS and final sign off is delayed due outstanding discussions with regard to Telephone licenses required, final requirement definition and absences of responsible parties.
  • SharePoint Development might primarily be conductible in June due to the limited availability of the resources from July onwards

Next Steps

  • Finalisation of requirements, submission and sign off of project brief
  • Kick off for SharePoint Development
  • Regular Meetings to start taking place from Mid June 2019 forthnightly
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
3.7 days
Activity this year
9.0 days
Activity to date
9.0 days
Estimate to complete current year
8.8 days
Estimate to complete future years
53.0 days

Project Info

Project
Clearing 2019
Code
USG013
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
Victoria Weinsberg
Project Sponsor
Rebecca Gaukroger
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
11-Mar-2019
Planning Date
06-May-2019
Delivery Date
06-Aug-2019
Close Date
25-Oct-2019
Overall Priority
Normal
Category
Compliance

Documentation