- Report Date
- April 2019
Achievements this period
- Securing SharePoint Development Resource for 10 days in the time between May - Aug 2019
- College Representatives and new Communication Rep clarified
Issues
Next Steps
- Meeting with College Representatives, SRA, PM and SharePoint Development Resource Mid May
- Regular Meetings to start taking place from Mid June 2019 forthnightly
- Approved budget
- 50.0 days
- Activity this month
- 3.7 days
- Activity this year
- 5.2 days
- Activity to date
- 5.2 days
- Estimate to complete current year
- 13.0 days
- Estimate to complete future years
- 58.3 days