Report for July 2015

Report Date
July 2015

Achievements this Period

  • Analysis report completed and reviewed by stakeholders
  • Project closed

 

Completion Report - here

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
5.0 days
Activity this month
3.5 days
Activity this year
3.8 days
Activity to date
3.8 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
D&A - ThankQ Analysis
Code
USG001
Programme
USG Portfolio Projects (OTHUSG)
Project Manager
David Watters
Project Sponsor
Pete Morrison
Current Stage
Close
Status
Closed
Start Date
23-Jun-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2015
Programme Priority
1
Overall Priority
Normal
Category
Discretionary