Report for June 2015

Report Date
June 2015

Achievements this Period

  • Project started and website created

Issues

  • None reported 

Next Steps

  • Project brief to be completed
  • Report to be completed

 

Milestones

03-Jul-2015Planning milestonePlan
24-Jul-2015Delivery milestoneDeliver
31-Jul-2015Project closureClose
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
5.0 days
Activity this month
0.3 days
Activity this year
0.3 days
Activity to date
0.3 days
Estimate to complete current year
4.7 days
Estimate to complete future years
0.0 days

Project Info

Project
D&A - ThankQ Analysis
Code
USG001
Programme
USG Portfolio Projects (OTHUSG)
Project Manager
David Watters
Project Sponsor
Pete Morrison
Current Stage
Close
Status
Closed
Start Date
23-Jun-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2015
Programme Priority
1
Overall Priority
Normal
Category
Discretionary