Report for Nov 2019
- Report Date
- November 2019
Achievements this period
- Limited progress - limited business resources while the Exams team focus on prep for the Dec 2019 exam diet
- Bug fixing and upgrade of Exam Web Timetables to new version of Python 3.6, Django 2.2 is in progress
Issues
- Slow performance in LIVE is being investigated by the IS Production
- Pending changes in Exam Scheduler Connect in TEST haven't yet been tested by the Exam business team
- Resource conflict for Project Manager with TTU017 Course Timetabling Scientia Upgrade
Next Steps
- WP2 - Exam team complete testing of Student system connector changes ( expect Dec 2019 earliest?)
- WP3 - project team continue working through the 10 JIRAS carried over from SAS005
- WP2 - deploy to LIVE during Jan 2020, ahead of start of scheduling of April / May exam diet
- Approved budget
- 25.0 days
- Activity this month
- 2.7 days
- Activity this year
- 15.0 days
- Activity to date
- 16.3 days
- Estimate to complete current year
- 8.5 days
- Estimate to complete future years
- 0.0 days