Report for Oct 2019
- Report Date
- October 2019
Achievements this period
- WP2 - Supplier tech consultant delivered the changes to the Student Systems connector in DEV & TEST (over 3 day booking on 18/21/22-Oct )
Issues
- WP2 - availability of Exams team for project testing - Exams team have one unfilled vacancy- testing can't start until the end of Nov
Next Steps
- WP2 - Exam team complete testing of Student system connector changes ( expect Nov / Dec 2019)
- WP3 - project team start working through the 10 JIRAS carried over from SAS005
- WP2 - deploy to LIVE during Jan 2020, ahead of start of scheduling of April / May exam diet
- Approved budget
- 25.0 days
- Activity this month
- 2.0 days
- Activity this year
- 12.0 days
- Activity to date
- 13.0 days
- Estimate to complete current year
- 23.0 days
- Estimate to complete future years
- 0.0 days