Current project status Report Date RAG Budget Effort Completed Effort to complete December 2019 AMBER 25.0 days 21.0 days 4.0 Content Status In Progress Current Stage Plan Start Date Friday, 19 July 2019 Planning Date Friday, 30 August 2019 Delivery Date Wednesday, 18 September 2019 Close Date Friday, 31 January 2020 Project information Project Code TTU019 Programme Timetabling (TTU) Session 19/20 18/19 Organisational Unit University Secretarys Group Project Management Office (if relevant) ISG PMO Responsibility Applications Development and Operations Overall Priority Normal