Report for September 2017

Report Date
September 2017

Achievements this period

  • Project Review Meeting held
  • Roll forward documentation reviewed and updated 
  • Closure report completed
  • Project closed

Issues

None

Next Steps

  • Obtain all closure report sign offs
  • Close Project

Milestones

Target Date Title
06-Oct-2017 Project Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
28.0 days
Activity this month
6.0 days
Activity this year
23.0 days
Activity to date
176.0 days
Estimate to complete current year
0.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Timetabling Service Annual Rebuild and Roll Forward to 17/18
Code
TTU014
Programme
Timetabling (TTU)
Management Office
ISG PMO
Project Manager
Susan Duff
Project Sponsor
Scott Rosie
Current Stage
Close
Status
Closed
Start Date
05-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Oct-2017
Programme Priority
1
Overall Priority
Highest
Category
Compliance