April 2016

Report Date
April 2016

Achievements in last period

  • Decommission IDM student feed and old Oracle satstage and spda signed off in Test.

 

Issues

Next Steps

  • Fix the remaining data issues and sign off decommission
  • Sign off and close

 

10-May-2016Deployment Sign Off-Maintenance completed
24-May-2016Closure
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Improvements to start of Semester 1 processing for Timetabling
Code
TTU011
Programme
Timetabling (TTU)
Project Manager
Franck Bergeret
Project Sponsor
Scott Rosie
Current Stage
Close
Status
Closed
Start Date
11-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Jul-2016
Programme Priority
3
Overall Priority
Normal
Category
Discretionary