February Report

Report Date
February 2016

Achievements in last period

  • Completed end to end integration and volume testing
  • Signed off Acceptance
  • Deployed to Live, but switching new SPDA on

Issues

  • resolved: go live issue highlighted during the synchronisation: there is a higher number of data to be updated, inserted or deleted. This required additional investigation to have reassurance before running the new SPDA for the 1st time. Delay to complete deployment:issue 8  

Next Steps

  • Monitor live
  • Reschedule deployment sign off and closure, will be delayed by 2 weeks
  • Revise estimates to take go live additional effort into account

 

24-Feb-2016Deployment
03-Mar-2016Deployment Sign Off-Maintenance completed
21-Mar-2016Closure
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
98.0 days
Activity this month
26.0 days
Activity this year
101.0 days
Activity to date
101.0 days
Estimate to complete current year
8.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Improvements to start of Semester 1 processing for Timetabling
Code
TTU011
Programme
Timetabling (TTU)
Project Manager
Franck Bergeret
Project Sponsor
Scott Rosie
Current Stage
Close
Status
Closed
Start Date
11-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Jul-2016
Programme Priority
3
Overall Priority
Normal
Category
Discretionary