February Report
- Report Date
- February 2016
Achievements in last period
- Completed end to end integration and volume testing
- Signed off Acceptance
- Deployed to Live, but switching new SPDA on
Issues
- resolved: go live issue highlighted during the synchronisation: there is a higher number of data to be updated, inserted or deleted. This required additional investigation to have reassurance before running the new SPDA for the 1st time. Delay to complete deployment:issue 8
Next Steps
- Monitor live
- Reschedule deployment sign off and closure, will be delayed by 2 weeks
- Revise estimates to take go live additional effort into account
| 24-Feb-2016 | Deployment |
| 03-Mar-2016 | Deployment Sign Off-Maintenance completed |
| 21-Mar-2016 | Closure |
- Approved budget
- 98.0 days
- Activity this month
- 26.0 days
- Activity this year
- 101.0 days
- Activity to date
- 101.0 days
- Estimate to complete current year
- 8.0 days
- Estimate to complete future years
- 0.0 days