March 2016

Report Date
March 2016

Project closed

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Timetabling Service- Scientia Upgrade
Code
TTU010
Programme
Timetabling (TTU)
Project Manager
Morna Findlay
Project Sponsor
Scott Rosie
Current Stage
Close
Status
Closed
Start Date
09-Jul-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Mar-2016
Programme Priority
1
Overall Priority
Higher
Category
Compliance