Report for February 2016
- Report Date
- February 2016
Achievements this period
- One JIRA issue closed
- New budget approved.
- CMDB updated
- requirement to update TAD due to changes made in this project transferred to TTU012
- project closure put forward for approval
Issues
None outstanding
Next Steps
Close project
RAG Status
The project status is AMBER due to issues of time, cost and scope which are now resolved.
- Approved budget
- 224.0 days
- Activity this month
- 3.0 days
- Activity this year
- 210.0 days
- Activity to date
- 222.0 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days