Report for February 2016

Report Date
February 2016

Achievements this period​

  • One JIRA issue  closed 
  • New budget approved.
  • CMDB updated
  • requirement to update TAD due to changes made in this project transferred to TTU012
  • project closure put forward for approval

 

Issues

None outstanding

 

Next Steps

Close project

 

RAG Status

The project status is AMBER due to issues of time, cost and scope which are now resolved.

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
224.0 days
Activity this month
3.0 days
Activity this year
210.0 days
Activity to date
222.0 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Timetabling Service- Scientia Upgrade
Code
TTU010
Programme
Timetabling (TTU)
Project Manager
Morna Findlay
Project Sponsor
Scott Rosie
Current Stage
Close
Status
Closed
Start Date
09-Jul-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Mar-2016
Programme Priority
1
Overall Priority
Higher
Category
Compliance