January Report

Report Date
January 2015

Achievements in Last Period

  • Deployed threshold check to test and acceptance signed off
  • Deployed threshold check into live
  • Closure signed off end January and final WIS approval on 6/2

Issues

  • none

Next Steps

  • WIS closure approval

 

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Timetabling - Incoming Interface Refinements
Code
TTU005
Programme
Timetabling (TTU)
Project Manager
Craig Middlemass
Project Sponsor
Scott Rosie
Current Stage
Close
Status
Closed
Start Date
07-Nov-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jan-2015
Programme Priority
2
Overall Priority
Normal
Category
Discretionary