Report for December 2014
- Report Date
- December 2014
Achievements in Last Period
- Last attempted at the email fix has been completed in Development with a plan to deploy to Test and Live in January.
Issues
- Reported as Amber as every issue that has been fixed has highlighted another issue (since May 2014) so Application Support are not willing to close the project. Currently the issue preventing closure is implementing a threshold check email.
Next Steps
- Deploy threshold check to test and acceptance sign off
- Deploy threshold check into live
- Close the project
Milestones
| 07-Jan-2015 | Deploy email fix to Test |
| 14-Jan-2015 | Deploy email fix to Live |
| 21-Jan-2015 | Closure |
- Approved budget
- 91.0 days
- Activity this month
- 0.3 days
- Activity this year
- 8.0 days
- Activity to date
- 89.1 days
- Estimate to complete current year
- 1.1 days
- Estimate to complete future years
- 0.0 days