- Report Date
- July 2014
Achievements in Last Period
- Swtichover of the web applications is complete (4 August)
- Switchover documentation complete and handed over to Technology Management
Issues
- Learn outgoing interface has encountered a problem in test, awaiting resolution before deploying to live
- Project reported as Red given carry over into 14/15 due to Learn feed failure
Next Steps
- Deliver the Learn outgoing feed into Live
- Project closure
Milestones