Report for June 2014
- Report Date
- June 2014
Achievements in Last Period
- Repointing of LEARN feed in LIVE
- Project budget increased to cover final steps
- Positive discussions round using Veeam solution for problem with rebuild of LIVE KB server
Issues
- Build of LIVE KB server encountered further issues
- Insufficient programme budget to cover installation of Veeam soultion to above issue
- Veeam solution moved to new project to start in August 2014
- Milestones revised to accommodate above issues
Next Steps
- Deployment sign-off
- Project closure
Milestones
| 17-Jul-2014 | Deployment Sign-Off Review | Deliver |
| 24-Jul-2014 | Project Closed | Close |
- Approved budget
- 149.0 days
- Activity this month
- 8.7 days
- Activity this year
- 148.1 days
- Activity to date
- 147.8 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days