Report for June 2014

Report Date
June 2014

Achievements in Last Period

  • Repointing of LEARN feed in LIVE
  • Project budget increased to cover final steps
  • Positive discussions round using Veeam solution for problem with rebuild of LIVE KB server

Issues

  • Build of LIVE KB server encountered further issues
  • Insufficient programme budget to cover installation of Veeam soultion to above issue
  • Veeam solution moved to new project to start in August 2014
  • Milestones revised to accommodate above issues

 

Next Steps

  • Deployment sign-off
  • Project closure

 

Milestones

17-Jul-2014Deployment Sign-Off ReviewDeliver
24-Jul-2014Project ClosedClose

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
149.0 days
Activity this month
8.7 days
Activity this year
148.1 days
Activity to date
147.8 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Timetabling Scientia Upgrade
Code
TTU002
Programme
Timetabling (TTU)
Project Manager
David Watters
Project Sponsor
Scott Rosie
Current Stage
Close
Status
Closed
Start Date
13-Sep-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2014
Programme Priority
2
Overall Priority
Higher
Category